Framework home · Policy document
Proposed conditions for a data centre
What the applicant must show
Provide coincident peak load (MW), annual demand (MWh), water demand by season and source, and a funded closure plan. Record who reviewed each estimate and which assumptions the utility accepted. IEA, Energy and AI (2025)
What would a 10 MW site mean in Jamaica?
Jamaica’s Office of Utilities Regulation reports that monthly system peaks ranged from 597.4 MW to 678.1 MW in 2024. An illustrative 10 MW site drawing its peak at the same time would equal about 1.5% of the highest monthly peak (10 ÷ 678.1). That comparison says nothing about spare capacity at a particular substation.
| Quantity | Basis | Decision use |
|---|---|---|
| 678.1 MW | Recorded 2024 system peak | Reference point for scale. |
| 10 MW | Illustrative maximum grid draw | Request a utility connection study. |
| 61,320 MWh/year | 10 MW × 70% load factor × 8,760 hours | Compare annual energy with the supplier’s tariff and supply mix. |
For regional context, the World Bank reported an average near US$0.25/kWh in 2024, with some countries above US$0.40/kWh. Obtain the site tariff, demand charges, taxes and connection costs before pricing a project.
Office of Utilities Regulation, Annual Report 2024–25, Table 20 · World Bank, Strategic investments for the energy transition in the Caribbean (2024)
A data centre has to keep working through an outage without placing an unagreed burden on the people who share its power, water and roads. Set the conditions for each stage of the project, and name the authority responsible for accepting the evidence.
Independent CAIA consultation guidance. It does not establish legal duties, issue approvals or replace applicable law and permit conditions. Treat the requirements below as proposed checks before a decision.
Screening: compare sites and options before committing
Start with the work the centre would serve and the people who need that service. Compare local construction, rented capacity and a staged build at the same workload and service standard. Map community water sources, schools, homes, sensitive habitats and roads alongside flood, coastal and extreme-heat exposure. Check whether power, fibre and access roads fail together. Share the environmental baseline and give neighbours a contact for concerns. In the Portmore assessment, cooling and site options are modelled; a new project still needs its own field measurements and permits.
Design: put the grid, water and neighbourhood on the same plan
Ask the utility for written agreement on peak site electricity demand, annual use and any upgrades. Include computing, cooling, battery charging and auxiliary equipment. Track how the load changes during hot afternoons, restart and prolonged outages. Compare direct water withdrawal, consumption and return flows in normal and dry periods. Name the source, existing users, available storage and shortage priority. Confirm the stormwater route under expected flood and backflow conditions. Check land disturbance, fuel spill exposure, local heat and noise at affected homes or habitats. For diesel and other backup sources, ask the environmental authority what pollutants to measure, such as nitrogen oxides and fine particles, where to measure them and when reporting is required. Account for routine tests and emergency operation separately.
Design: agree trade-offs and who pays
Compare cooling options against the same useful computing work and weather. A design that uses less electricity may draw more water in a dry month. An onsite generator can preserve service through a grid failure and raise local air pollution and noise when running. A battery can shift or cover some loads. Record how long it can carry the agreed load and what safety measures apply. Publish the approved limits and identify the party paying for utility upgrades, monitoring, cleanup and alternate services. Treat projection figures as estimates until meters, seasonal samples and operational drills are available.
Before opening: train staff and test recovery
Name a facility manager, operations lead, safety lead, security lead and approved backup for each role. Require paid practice with the written operating procedures. Include maintenance handover, incident reporting, communications and continuity during a severe-weather closure. Verify who can pause the service and who may authorise restart. Test loss of power, cooling or connectivity without affecting live users. Test whether the backup can carry the minimum agreed service after a common route fails. Assign the emergency contact and use the local authority’s response process. Commissioning checks show what happened in the tested conditions; keep unresolved faults on the opening decision.
Operation: protect data and check what the site actually uses
Record the physical facility address available to authorised purchasers and regulators, and every jurisdiction where records, backups or supplier support access may be located. Publish the information that is lawful and safe to disclose. Confirm local laws, licences, labour and safety duties, data protection, security responsibilities and reporting routes. Keep an inventory of who acts on each record and how permissions are withdrawn. Rehearse secure export and restoration to another approved provider. Check electricity and water meters against the agreed boundary. Compare air, heat, noise and runoff readings with the site baseline and applicable thresholds. Name the person who must act if a threshold is reached.
Closure and replacement: disposition is part of the cost
Maintain a dated asset register for batteries, servers, drives and equipment containing controlled materials. Plan periodic replacement, certified media handling and documented routes for reuse, recycling or disposal. Check which local permits and any Basel Convention procedures apply before a cross-border waste transfer; the destination matters. Set aside resources for the final shutdown, customer-data transfer or deletion, lawful retention, removal and land restoration. Verify completion with the responsible authorities and affected clients. An untested recovery route or an unexplained waste destination is a reason to delay transition.
Evidence to collect before approval
- At site selection, obtain a documented grid review, dry-period water review, hazard assessment and public contact route. Compare alternatives before publishing the selection rationale.
- Before opening, record the accountable operator, approved limits, trained deputies and witnessed results of emergency recovery exercises.
- During operation, publish agreed monitoring and incident summaries with lawful redactions. If a limit is exceeded, follow the applicable permit or response plan and record evidence before restart.
- Before accepting decommissioning, verify approved data disposition, equipment records, any required transfer permissions and environmental closeout.
Measures to report
- Peak site electricity demand in MW over a named interval; annual site electricity in MWh; record grid and onsite generation separately.
- Water withdrawn, consumed and returned in cubic metres from or to each named source; report daily maxima and dry-period totals against a stated accounting boundary.
- Air pollutant concentrations in units specified by the competent authority, generator hours, and noise in dB(A) at named receptors and periods; retain relevant meteorology and approved measurement conditions.
- Discharges and stormwater observations against the site permit or agreed baseline. Track the time to complete fallback and the maximum recorded interval of lost data in recovery exercises.
- Track incidents, capability coverage by role, and the share of retired assets with a verified disposition record.
Terms used here
- Peak demand
- Highest rate of electricity use during the stated metering interval, measured in megawatts (MW).
- Megawatt-hour
- Energy equivalent to a one-megawatt load running for one hour.
- Water withdrawal
- Water taken from a named source over a stated time.
- Water consumption
- Withdrawn water not returned within the declared water-accounting boundary and period.
- Receptor
- A location where people or the environment may be affected, such as a home, school or sensitive habitat.
- Recovery time objective
- The target time to restore a service after disruption. It is not an observed recovery time.
- Decommissioning
- The planned shutdown, removal, disposition and closeout of a facility or service.
Sources
- International Energy Agency, Energy and AI
- IFC General Environmental, Health and Safety Guidelines
- UNEP Cartagena Convention and protocols
- Basel Convention e-waste amendments
- Dunkley and Dunkley, Portmore data-centre assessment
- CAIA Caribbean AI Safety and Alignment guidance
- NIST Cybersecurity Framework 2.0
- CDEMA Regional Response Mechanism